Countdown to Hospital of the Future

In this Section

 


The new Columbia St. Mary's Hospital Milwaukee is nestled into the Lake Drive skyline as seen from the neighboring Water Tower Park.


There are twelve specially-designed surgical suites in the new hospital, with space available to build out four more in the future. Both the doors and the sanitizing station (on the right) offers a view into the room.

 


The design of the new operating rooms provide the space needed to create fully digital operating suites which help physicians perform patient procedures more efficiently and effectively.

 


The nursing station is centrally located on each unit to serve all patients. Work space is also available for staff on countertops built between patient rooms.

Photos by Jim Brozek.

Countdown to the "Hospital of the Future"

July Construction Milestones

  • Installation of the porcelain tile at the front and back entrances complete.
  • Final cleaning underway of: the 7th floor, 6th floor, portion of the 5th floor, Pre- and Post-Operative, Pre- and Post-Procdural and 1st floor.
  • Installation of final finishes, doors and hardware at the 3rd floor Imaging/Invasive area.
  • Completion of the landscaping along North Avenue and a portion of the Main Entrance.
  • Completion of drywall installation at the 5th floor Behavioral Unit.
  • Completion of the architectural finishes for the Dining Room on the ground level.
  • Installation of owner vendor medical equipment in the Emergency Department.

Check back each month for new construction photos and milestones!

The new Columbia St. Mary's Hospital Milwaukee opens Fall 2010!

Opening in 2010, this ground-breaking project consolidates Columbia St. Mary’s Columbia and current Lake Drive campuses into one. The new Columbia St. Mary’s Hospital Milwaukee will provide the blueprint for healthcare transformation in our community.

The evidence-based design of our new East Side hospital will improve patient outcomes, increase patient satisfaction and aid in the recruitment and retention of top quality staff. In addition, the consolidation will lead to $19 million in annual savings to the organization leading to more affordable health care for everyone.

Help us go "Above and Beyond!"

Columbia St. Mary’s Foundation is committed to helping the new East Side hospital go “Above and Beyond” by funding advanced treatments and technologies, as well as enhancements to create an exceptional patient experience. Make a gift!

 

 


2010 Construction Milestones

As we look forward to opening our new, consolidated hospital in Fall 2010, many exciting milestones have been reached.

June 2010:

  • Completed flooring and painting at the front entrance lobby and concourse.
  • Substanially completed 4th floor peri-operative rooms.
  • Substanially completed 2nd floor.
  • Substanially completed 1st floor.
  • Commissioned air handler units throughout the building.
  • Hung and finished drywall at 5th floor Behaviorial Health unit.
  • Started construction of 8th floor Sacred Heart Rehabilitation Institiute.

May 2010:

  • Completed 4th floor surgical suites. Prepared for medical equipment.
  • Acute care patient rooms substantially completed on 6th and 7th floors.
  • Ground floor kitchen is 75 percent complete.
  • Installation of ceilings and flooring underway at the ground floor Emergency Department.
  • "Living Garden" installation began on May 18 above the main entrance lobby.

April 2010:

  • Operating rooms ready for medical equipment installation to begin on May 3, 2010.
  • Completed installation of the lead-lined drywall at 3rd floor Imaging.
  • Finished installation of soft and hard ceilings from the main entrance to the discreet drop off area of the hospital.
  • Completed construction of the 5th & 6th floor acute care patient levels.
  • Completed construction of the glass handrail system and pavers at the three terraces located along North Avenue.

March 2010:

  • Completed ceiling tile and flooring on 7th floor.
  • Completed drywall finishing and prime paint/1st coat in the Operating Rooms.
  • Installed lead drywall at 3rd floor imaging.
  • Installation of ceilings and overhead inspections at Emergency Department.
  • Start installing ceiling tile and floors on the 6th floor.
  • Continued installing millwork and accessories through out the facility.

February 2010:

  • Emergency Department painted.
  • Headwalls and flooring installed in patient rooms.
  • Kitchen construction significantly underway.
  • Drywall installed in Imaging and Invasive areas of the 3rd floor.
  • Departments moved, including CSM Foundation, to the Heritage Center (formerly the Historic East Facility).

January 2010:

  • Final demolition on the Lake Drive campus completed. The two-story Todd Wehr Diagnostic Center torn down to prepare for final construction of the new hospital.
  • Major progress of drywall installation in the atrium, bed tower and emergency department areas completed.
 